2K HOUSE BLOG
BACKGROUND
Problem
Statement
This project
is very unique in the fact that it is a tiny home, but with much more scope and
purpose than most tiny homes. Most tiny
homes are for people that are just minimalists that want to make a small footprint;
however our tiny house project has much more purpose. We are doing research on tiny homes for
$2,000 which can serve the purpose of giving families homes that are victims of
natural disasters. By be conscientious
of natural disasters and working with partners like Alabama Rural Ministry and
FEMA, we feel that we will be able to deliver a home that is not only
economical, but could change the life of many families that are subject to
disaster.
PRIMARY DUTIES
Team
Work
This project
is going to be executed by our 13 person studio group which is divided into
four different teams. These teams
consist of Pre-Planning, Conceptual Design, Final Design, &
Implementation. The Preconstruction
schedule is split into 4 weeks which will give each team one week to work on
the home before we begin constructing our final project. My team was the Implementation team which had
many different duties to complete during our last week of preconstruction.
The first
task that we had to complete was a safety plan and a work plan for every team
throughout construction in order to keep everyone working in an efficient and
safe manner. This safety plan was very
extensive, and included all forms of protection, best practices, and emergency
reactive procedures for any event that could have happened during
construction. The work plan came about
from the safety plan and allowed us to separate the teams into more efficient
work crews in order to get the work completed.
The next step
was to start the site work before everyone came out onsite to construct the
building. This consisted of plotting out a building lot, leveling ground,
setting foundations, and organizing site zones.
By planning upfront and ensuring correct foundations, the home
construction went much faster. Aside
from my team work, I also had individual responsibilities that I was held
accountable for. Before construction I
made a BIM model of the home, a material take-off, an estimate, and provided
each team with the latest construction drawings. I was the individual with keys to the site,
so I had to be the first one there and the last one to leave every day in order
to mobilize and demobilize each day. I
also have significant construction site experience, so I was assigned to be a
foreman of one construction crew to give direction, instruction, training, and
assure quality assurance. As
construction progressed I performed tasks such as foundations, waste
management, documentation, framing, sheathing, siding, roofing, and finish
work; by everyone participating in each element of the process, we all got a
well-rounded experience and understanding of the construction process.
RESEARCH ISSUE
Spatiality
One challenge
of tiny homes is the simple fact that they are tiny and are difficult to make
comfortable for more than one person.
Since our house is so small, we are not going to be able to create
specific “rooms”, but just split the home up by curtains and material
changes. One problem with including
doors is the wasted space that the door swings take up; since this home is a
maximum of 400 square feet, we do not have the room to waste. The only way to overcome this challenge while
still keeping doors is to put in pocket doors, but the partitions are not wide
enough to allow the door to slide, making this impossible. Therefore, we will have to put in either
curtains, or try to split rooms by material changes.
If the home
has no separation or privacy, then the home serves no purpose because it will
only accommodate for one person. The
purpose of this project is not to just make a living space for one person, but
a living space for a small family from 2 – 4 people. According to the article that I found on a
couple that lived in a tiny home together, this is a challenge even for a
married couple. Even a married couple
needs separation at times for things such as hobbies, work, and relaxing; these
types of activities are impossible to do in a tiny home because there is just
not enough room. Also, budgets are so
tight on tiny homes there is typically no running water, sewer, and limited
power.
I began to
brainstorm about ways to overcome these challenges, which was very difficult to
get started. What I started to find is
that there is standard way to build a tiny home, there are infinite
possibilities and many creative solutions.
Since our budget is $2,000, I don’t think that we will be able to any
systems in the home but we will be able to plan for future systems. As I searched many different systems, there
are many that are inexpensive, but they are not conventional and I don’t want
the occupants to feel inferior by using unconventional systems. I believe the best solutions are to run these
homes with RV and trailer solutions.
This is a convenient way to get water, power, sewer, heat, and AC while
keeping the costs low and feeling like the systems are conventional rather than
compromising.
http://tiny-project.com/tiny-house-roommates-living-with-your-partner/
REFLECTION ON THE PROJECT
When
were you most engaged? Least engaged? Why?
I was very
engaged throughout the entire process of the home because I wanted to learn as
much as possible about every aspect of the home. I started by helping with the design and
making construction drawings, and then materials and prices. During the site and foundations I was very
involved because I had the keys to the site and the plans for the
foundations. We then moved onto the
framing in which I was very involved with the walls, but not the floor. This is where we really ran into issues of
deferring from the model and problems started to arise. My intention with the framing was to align
every member from the floor to the roof, which didn’t happen because some
things were framed incorrect. This is
where I started to become disengaged because everyone was pointing fingers, no
problems were being solved, just attitudes arising so I checked out. I began to become upset with the attitude and
carelessness of everyone around the project.
Many individuals would show up late and put in the minimum time and
leave. Towards the end of the project
there were about half as many people onsite as there were in the beginning and
I became much more involved then because I wanted to get done and I knew that I
needed to take a charge or that would not happen.
I think that
I was engaged in the project when people were motivated and wanted to have high
production. As the project lost momentum
and problems arose I began to become unengaged because I felt nobody
cared. Finally I ended the project
strong because I could see the end and wanted to finish.
What
surprised you about the project?
Throughout
the duration of the project, I was surprised with many different things that occurred. One being that many of the building science
students had never been exposed to actual construction and they had a hard
learning curve because they had never seen these activities in real life.
Another thing
that surprised me is how much we deviated from the drawings with such a small
plan. This house was a 160 square foot
home and we only did the building envelope; however we still managed to change
the drawings significantly throughout the process. This just shows how so many change orders and
RFI’s happen in the real world regardless of how perfect you think the drawings
are.
Who/What
contributed to your learning on the project? Why?
I thought it
was very interesting to see the different leaders that emerged throughout the
process of construction and see how they dealt with conflict. Due to experience in certain parts of
construction, someone would take charge of that portion of construction. Some leaders would get angry and point
fingers at others when something would go wrong, while others would go pout in
the corner and think the issue was going to resolve itself. This was interesting to me because it taught
me to look at the way things are done and how issues are dealt with and try to
resolve them in a more efficient manner.
One other
thing that I really learned was to really just pay attention to detail before
construction. I did most of the drawings
prior to construction and I noticed that I just would draw something that
looked good on paper, but didn’t necessarily work in the field. And more importantly, not think over the
entire detail; for example I drew all the framing and sheathing, but no
waterproofing or details of connections.
These types of things are essential to have thought through strenuously
BEFORE construction starts.
What
would you suggest for additional projects of this type?
I think that
one thing that this project lacked was buy-in from everyone on the team which
is essential to having a successful project.
So many students were checked out before this project, the project was driven
by only a few who really wanted to do it.
I think at times during construction we had too many people and it made
things difficult, but that was only because those people didn’t care about
production, they just wanted to put their time in and leave. Also, my team got the house plan from the “Final
Design” team and there were absolutely no details in the plan. There was no flashing, wall sections,
cladding, waterproofing, foundations, connections, etc. This made it much more difficult
for my team because we were scrambling to do our week tasks, plus the left over
tasks from other teams.
In summary,
the most important thing that this project was missing was preplanning. We needed a team that cared about a
successful project, and was excited about getting a successful end product
which we lacked. From details of
moisture, connections, sections, and material choices. The sections that are used in a project like
this cannot just be a standard section; for example the corner flashing on the
building – the flashing oil canned extremely bad because we didn’t think
through the material choice – with that material choice, we would have been better
to put a furring strip behind the flashing, used flat headed screws, and
predrilled holes to ensure that there was an attractive end product with no oil
canning.
Overall I had
a great time building this house, and I learned a ton about planning, reality, construction,
materials, sequencing, and teams. I will
definitely build one again and try to fix all the mistakes that happened on
this home.
No comments:
Post a Comment