2K House Project
Background:
This construction project was an opportunity for MIDC
students to design and build an efficient prototype home for the tornado
victims in the surrounding areas of Alabama
while gaining experience with the major challenges inherent in a construction
project. We started with a plan to design a 400 SFT house project and had a
budget of about $2,000. Over the course of five weeks, as we progressed with
the planning and designing of this project, our ideas evolved, and we finally ended
up constructing a 160 SFT house for such an ambitious budget.
Primary Duties:
At the very beginning of the project, we divided ourselves
into four groups (3/4 people in each group) where each group was responsible
for different project activities such as Programming/Planning, Schematic design,
Construction Documents and Implementation. The goal was to perform
preconstruction activities in smaller groups during the first few weeks and
then build the house collectively as a class in two weeks. I was involved in
the schematic design phase of the project where we outlined the requirements
and overall program for the project, prepared study drawings and 3D models to
illustrate the concept and also estimated cost based on our concept. Best
suitable option for the assigned budget was created at the end of the schematic
design phase and then design moved forward to the design development phase.
During the Implementation stage of the project, I helped my teammates with
creating a construction work plan. This plan helped us further to understand
daily activities on the construction site. Once construction started on the
site I tried to engage myself in almost every activity performed on the site.
This helped me understand the various skill trades involved in the construction
of this project.
Research Issue:
A big challenge for us during schematic design phase was to
design a livable space within only 400 SFT of area with a very tight project
budget. Like most other building construction projects, there were limited funds
available for the construction of this prototype. This limit had a major
influence on the design decisions from building size and configuration to
material selection and detailing. To maintain the budget of $2000 we reduced
interior walls and created spaces using furniture units and curtains. Number of
doors and windows were restricted in order to reduce the construction cost.
Shape and size of the house was designed in such a way that it could be built
in a short period of time and easily moved from one place to another on a
trailer.
Reflection on the Project:
1. When were you most engaged? Who /What contributed to your
learning on this project and why?
I was most engaged during the schematic design/ Programming,
Planning stage of the project. We, as a group analyzed different case studies
for Tiny Homes and created a program for “Our House.” We prepared different
design options and finalized one which was suitable for the assigned budget of
$2000. I was also involved in making detailed study plans and 3D models to
illustrate concept of “Our house.” During the construction phase of the project
I learnt so many things about construction processes and assembly of different
parts of the building from foundations to structural wood framing. My construction
counterparts helped me to understand different construction techniques and
right ways of doing things on the site.
2. When were you least engaged?
I was involved in almost all of the phases in some way,
however small my involvement was. This was the best part of this exercise.
3. What surprised you about this project?
Project requirements and parameters were changed at
different stages of the project. Initially we started with the 400 SFT floor
area which further reduced to 160 SFT to accommodate the tight budget. Different
changes were made in the drawings/ details during the construction of the
house. Some decisions were taken on the site first and drawings were modified
accordingly which should have been the other way around.
4. What would you suggest for additional projects of this
type?
This project though small in size, gave us an opportunity to
experience every single stage of building construction project from its
conception to the execution. I realized that in order to complete a project
successfully, design and construction can not be thought as two consecutive
phases. Rather, these should collaborate and communicate with each other more
often. I think, we lacked this collaboration between the different phases, somewhere
during the process which resulted in slowing down the construction process.
However, with any project undertaken, there are always
lessons learned which help us make better decisions and tackle issues
differently. I would say, I am now more confident to work on a similar project
in the future.
No comments:
Post a Comment